101.

Zero duration activities but are assumed to start at the same time as the first and the end at the same time as the last one is called__________ activity.

A. hijacked.
B. heuristic.
C. hammocked.
D. hole.
Answer» C. hammocked.
102.

……………..is called if subsequent have the time by which an activity may be delayed without affecting.

A. action float.
B. terminal float.
C. free float
D. null float
Answer» C. free float
103.

_________ activities on the network diagram have zero duration and use no resources.

A. dangling.
B. dummy.
C. null.
D. zero.
Answer» B. dummy.
104.

____________is part of Risk Management.

A. risk analysis and risk estimation.
B. risk control and risk planning.
C. risk identification and monitoring.
D. risk control, planning, identification and monitoring.
Answer» D. risk control, planning, identification and monitoring.
105.

The activities have zero duration but are assumed to start at the same
time as the first and the end at the same time as the last one is
called__________ activity.

A. hijacked.
B. heuristic.
C. hammocked.
D. hole.
Answer» C. hammocked.
106.

____ is carried out to calculate the earliest dates on which each activity may be started and completed.

A. backward pass.
B. forward pass.
C. no pass.
D. increasing pass.
Answer» B. forward pass.
107.

In Software Prototype, ___________ means copies of input screens are shown to the users on a workstation, but the screens cannot actually be used.

A. simulation.
B. annealing.
C. mock-ups.
D. rad system.
Answer» C. mock-ups.
108.

. In software prototype, partial working model is classified into ________.

A. vertical and horizontal.
B. vertical and straight.
C. bended and horizontal.
D. elevated and horizontal.
Answer» A. vertical and horizontal.
109.

. The scope of the deliverables for an increment is rigidly constrained by an agreed deadline called as ____________.

A. sand boxing.
B. time boxing.
C. time delaying.
D. local delaying.
Answer» B. time boxing.
110.

. SSADM means ___________.

A. straight systems analysis design method.
B. structured systems analysis design method.
C. software systems analysis design method.
D. solutions systems analysis design method.
Answer» B. structured systems analysis design method.
111.

Sometimes redesigns of the code is often called as ________.

A. refactoring.
B. redesigning.
C. recoding.
D. rearranging.
Answer» A. refactoring.
112.

Find the two levels of development suggested by Booch ?

A. micro and macro processes.
B. inter and intra processes.
C. internal and external processes.
D. small and large processes.
Answer» A. micro and macro processes.
113.

________ is refined by Barry Boehm and his co-workers.

A. cocomo iii.
B. cocomo iv.
C. cocomo ii.
D. cocomo i.
Answer» B. cocomo iv.
114.

CPM can be expanded as _______.

A. control path method.
B. critical path method.
C. cohesion path method.
D. control path model.
Answer» B. critical path method.
115.

he Cost Benefit Analysis is done for ___________ feasibility.

A. social
B. technical.
C. programm
D. economical.
Answer» D. economical.
116.

One can_______ is classified into Functional and Non-functional.

A. project.
B. requirements.
C. start date. .
D. risk
Answer» B. requirements.
117.

Security (backups, firewall) will be a ________ requirement.

A. functional.
B. non-functional.
C. normal.
D. security.
Answer» B. non-functional.
118.

Time behaviour is the sub-characteristics of _______.

A. maintainability.
B. efficiency.
C. usability.
D. reliability.
Answer» B. efficiency.
119.

________ a set of attributes (data items) and that will be manipulated within the software (system).

A. instance.
B. class.
C. object.
D. data.
Answer» C. object.
120.

_________ indicates the connectedness of the system that can be derived mechanically.

A. dependency.
B. re-occurrence.
C. inheritance
D. relationship.
Answer» D. relationship.
121.

Diagrammatic form for Flow oriented Modelling………

A. functional diagrams.
B. er diagrams.
C. data flow diagrams.
D. system flow diagrams.
Answer» C. data flow diagrams.
122.

The sub-characteristics of efficiency is …..

A. understandability.
B. learnability.
C. resource utilization.
D. accuracy.
Answer» C. resource utilization.
Tags
  • Question and answers in Business Policy and Project Management,
  • Business Policy and Project Management multiple choice questions and answers,
  • Business Policy and Project Management Important MCQs,
  • Solved MCQs for Business Policy and Project Management,
  • Business Policy and Project Management MCQs with answers PDF download