101. |
The notice inviting tender should published in minimum........ daily news paper |
A. | 3 |
B. | 2 |
C. | 4 |
D. | 5 |
Answer» B. 2 |
102. |
Who will sign the contract deed on behalf of government |
A. | Chief engineer |
B. | Superintendent engineer |
C. | Executive engineer |
D. | Head clerk |
Answer» C. Executive engineer |
103. |
Who will draft contract agreement? |
A. | Chief engineer |
B. | Divisional head clerk |
C. | Executive engineer |
D. | None of the above |
Answer» B. Divisional head clerk |
104. |
Which are the criteria to be checked for pre- qualification of contractor |
A. | Financial strength |
B. | Past five year experience |
C. | Technical personnel engaged |
D. | All of the above |
Answer» D. All of the above |
105. |
How many envelops are required to submitted Tender form |
A. | 3 |
B. | 1 |
C. | 4 |
D. | 2 |
Answer» C. 4 |
106. |
Total no of grades for registration of contractor with governments are |
A. | 3 |
B. | 5 |
C. | 7 |
D. | 4 |
Answer» C. 7 |
107. |
Contract is terminated in case of |
A. | Slow progress and time limit exceeds |
B. | Work is not being executed as per specifications and instruction of EIC |
C. | Contractor tries to admit sub-contractor |
D. | All of the above |
Answer» D. All of the above |
108. |
Form no .........is used for material at site account |
A. | 35 |
B. | 28 |
C. | 16 |
D. | 9 |
Answer» A. 35 |
109. |
Mobilization advance |
A. | Shall be 2 to 5 % of project cost. |
B. | Shall be 3 to 7 % of project cost. |
C. | Shall be 10 to 15 % of project cost. |
D. | Shall be 12 to 18 % of project cost. |
Answer» A. Shall be 2 to 5 % of project cost. |
110. |
Stock account is cleared yearly while tools and plants account is cleared half yearly |
A. | TRUE |
B. | FALSE |
C. | none |
D. | all |
Answer» B. FALSE |
111. |
PERT analysis is based upon |
A. | Optimistic time |
B. | Pessimistic time |
C. | Most likely time |
D. | All of the above |
Answer» D. All of the above |
112. |
The time activity consumes in most adverse conditions is |
A. | Optimistic time |
B. | Pessimistic time |
C. | Most likely time |
D. | All of the above |
Answer» B. Pessimistic time |
113. |
The time activity consumes in normal conditions is |
A. | Optimistic time |
B. | Pessimistic time |
C. | Most likely time |
D. | All of the above |
Answer» C. Most likely time |
114. |
The difference between the total float and free float is called |
A. | Duration |
B. | Interfering float |
C. | Critical activity |
D. | None of the above |
Answer» B. Interfering float |
115. |
The critical path is |
A. | The longest path of the network |
B. | The shortest path of the network |
C. | The average duration path of the network |
D. | None of the above |
Answer» A. The longest path of the network |
116. |
The float of critical activity is always |
A. | Maximum |
B. | Minimum |
C. | Zero |
D. | None of the above |
Answer» C. Zero |
117. |
A dummy activity in a network |
A. | Is represented by dotted line |
B. | Is an artificial activity |
C. | Does not consume time and resources |
D. | All of the above |
Answer» D. All of the above |
118. |
Activity starts from |
A. | Head event |
B. | Tail event |
C. | Dual role event |
D. | None of the above |
Answer» B. Tail event |
119. |
Which of the following is an activity |
A. | Excavation |
B. | Curing |
C. | Laying concrete |
D. | All of the above |
Answer» D. All of the above |
120. |
Earliest start time of activity equals to |
A. | TE of tail event of an activity |
B. | TE of head event of an activity |
C. | Average time of TE of tail event and head event |
D. | None of the above |
Answer» A. TE of tail event of an activity |
121. |
................is provided to safeguard scaffolding against overturning. |
A. | Standards |
B. | Inclined rackers |
C. | Put-logs |
D. | Rails |
Answer» B. Inclined rackers |
122. |
Ladder leading to landing should be extended at least ....... meter above the landing |
A. | 1.2 |
B. | 1.5 |
C. | 1 |
D. | 1.8 |
Answer» C. 1 |
123. |
While using ladder one should not lean sideways more than......... cms. |
A. | 40 |
B. | 60 |
C. | 30 |
D. | 45 |
Answer» C. 30 |
124. |
Wooden ladders should be inspected at least........... a month. |
A. | Once |
B. | Twice |
C. | Three times |
D. | Four times |
Answer» A. Once |
125. |
In sheds for ceiling works, ......................... scaffolding is economical. |
A. | Suspended |
B. | Needle |
C. | Ordinary |
D. | None of the above |
Answer» A. Suspended |
126. |
The construction industry has accounted for about ............% of all deaths due to accident at place of work |
A. | 5 |
B. | 20 |
C. | 25 |
D. | 30 |
Answer» B. 20 |
127. |
For repair works at high level of multistoreyed buildings needle scaffolding is preferred |
A. | As it is more stable |
B. | As it looks better |
C. | As it will not obstruct traffic at ground level. |
D. | None of the above |
Answer» C. As it will not obstruct traffic at ground level. |
128. |
PPE stands for |
A. | Personal protective equipment |
B. | Preferred protective equipment |
C. | Prohibited protective equipment |
D. | None of the above |
Answer» A. Personal protective equipment |
129. |
For work at height one should use |
A. | Safety belt |
B. | Full body harness |
C. | none |
D. | all |
Answer» B. Full body harness |
130. |
A good safety record can produce higher morale, productivity and stronger employee loyalty. |
A. | Right |
B. | Wrong |
C. | none |
D. | all |
Answer» A. Right |
131. |
Who plays a crucial role in convincing the operating staff to adopt the change? |
A. | HRD manager |
B. | Junior engineer |
C. | Public relation officer |
D. | Supervisor |
Answer» D. Supervisor |
132. |
Supervisor is at the lowest level of management |
A. | Right |
B. | Wrong |
C. | none |
D. | all |
Answer» A. Right |
133. |
............. has 3 roles ;Trainer,Motivator and Facilitator |
A. | HRD manager |
B. | Junior engineer |
C. | Public relation officer |
D. | Supervisor |
Answer» D. Supervisor |
134. |
HRD is mainly concerned with |
A. | Optimum stress |
B. | Optimum cost |
C. | Optimum duration |
D. | None of the above |
Answer» A. Optimum stress |
135. |
Which one of the following is not a system of HRD |
A. | Optimization of resources system |
B. | Appraisal system |
C. | Carrier system |
D. | Training System |
Answer» A. Optimization of resources system |
136. |
Human resource is a |
A. | Perishable resource |
B. | Dynamic resource |
C. | Both A and B |
D. | None of the above |
Answer» C. Both A and B |
137. |
Human resource development (HRD) is a |
A. | Process |
B. | Previlege |
C. | Business cycle |
D. | None of the above |
Answer» A. Process |
138. |
HRD is a process which progresses by |
A. | Proper management of resource |
B. | customer satisfaction |
C. | Time resource optimization |
D. | Performance appraisal,Counseling and training |
Answer» D. Performance appraisal,Counseling and training |
139. |
MIS stands for |
A. | Management Innovation System |
B. | Management Information System |
C. | Management Interaction style |
D. | None of the above |
Answer» B. Management Information System |
140. |
HRD stands for |
A. | Human resource development |
B. | Human resource design |
C. | Higher resource development |
D. | None of the above |
Answer» A. Human resource development |
141. |
In one stack not more than.......... cement bags should be stored one above other. |
A. | 8 |
B. | 10 |
C. | 15 |
D. | 12 |
Answer» D. 12 |
142. |
The space between the walls and cement bags all-round should be at least......... cms. |
A. | 30 |
B. | 50 |
C. | 60 |
D. | 40 |
Answer» A. 30 |
143. |
EOQ stands for |
A. | Equal order quantity |
B. | Economic order quantity |
C. | Extra order quantity |
D. | None of the above |
Answer» B. Economic order quantity |
144. |
Timber and plywood should be stacked separately. |
A. | Agree |
B. | Disagree |
C. | none |
D. | all |
Answer» A. Agree |
145. |
In any construction project the material cost constitute about..... % of the total project cost. |
A. | 60 |
B. | 25 |
C. | 35 |
D. | 45 |
Answer» A. 60 |
146. |
While placing of concrete, it should not be dropped from more than .......m height. |
A. | 2 |
B. | 1 |
C. | 3 |
D. | 4 |
Answer» B. 1 |
147. |
The coarse aggregates of different sizes like 5 to 10 mm, 10 to 20 mm, 20 to 40 mm etc. should be stored in different piles. |
A. | Agree |
B. | Disagree |
C. | none |
D. | all |
Answer» A. Agree |
148. |
Which of the following is not a principle of preparing job layout |
A. | Location of auditorium |
B. | Administrative block |
C. | Warehouses/godown |
D. | Entry and Exit |
Answer» A. Location of auditorium |
149. |
Which of the following is not a purpose of making job layout |
A. | To develop human resources in organization |
B. | To save time of delivery of material |
C. | To safeguard material from wastage and theft |
D. | To keep lead minimum |
Answer» A. To develop human resources in organization |
Done Studing? Take A Test.
Great job completing your study session! Now it's time to put your knowledge to the test. Challenge yourself, see how much you've learned, and identify areas for improvement. Don’t worry, this is all part of the journey to mastery. Ready for the next step? Take a quiz to solidify what you've just studied.