Select the incorrect statement. |
| A. | Start float and finish float are always equal. |
| B. | Total float can be either start float or finish float. |
| C. | Start float and finish float need not be equal. |
| D. | Start float and finish float are the differences between activity times and notevent times. |
| Answer» C. Start float and finish float need not be equal. | |