Q. |
Select the incorrect statement. |
A. | Earliest start of an activity is the early event time of the node itleaves. |
B. | Latest finish of an activity is the late event time of the node it enters. |
C. | Latest start of an activity is its latest finish minus its duration. |
D. | None of the above |
Answer» D. None of the above |