Pick up the incorrect statement from the following: |
A. | The difference between the earliest start time and latest finish time of any activity, is the maximum time available for the activity |
B. | The difference between the maximum time available for the job and actual time it consumes, is called total float |
C. | The difference between the latest start time and earliest start time of an activity, is called total float |
D. | None of these |
Answer» D. None of these |