Q. |
Select the correct statement. |
A. | Activity arrows in a CPM network are drawn to scale |
B. | The tail of an arrow represents the finish of anactivity |
C. | Arrow bead represents the start of an activity |
D. | None of the above |
Answer» D. None of the above |