Select the correct statement. |
| A. | Activity arrows in a CPM network are drawn to scale |
| B. | The tail of an arrow represents the finish of anactivity |
| C. | Arrow bead represents the start of an activity |
| D. | None of the above |
| Answer» D. None of the above | |