Pick up the incorrect statement from the following: |
A. | An activity of a project is denoted by an arrow on the net work |
B. | The tail of the arrow indicates the start of the activity |
C. | The head of the arrow indicates the end of the activity |
D. | The arrows are drawn to scale from left to right |
Answer» D. The arrows are drawn to scale from left to right |