Q.

The reduction in project time normally results in

A. Decreasing the direct cost and increasing indirect cost
B. Increasing the direct cost and decreasing the indirect cost
C. Increasing the direct cost and indirect cost both
D. Decreasing the direct cost and indirect cost both
Answer» B. Increasing the direct cost and decreasing the indirect cost