222
109.7k

480+ Cost Accounting Solved MCQs

These multiple-choice questions (MCQs) are designed to enhance your knowledge and understanding in the following areas: Bachelor of Management Studies (BMS) , Bachelor of Accounting and Finance (BAF) , Bachelor of Commerce (B Com) .

451.

In this type of costing works are carried out at factory premises:

A. Job
B. Contract
C. Batch
D. Process
Answer» A. Job
452.

Under this method, homogeneous products are taken as cost unit

A. Job
B. Contract
C. Batch
D. Process
Answer» C. Batch
453.

The costing method which can be used in industry where the product passes through different processes is known as

A. Job costing
B. Operating costing
C. Batch costing
D. Process costing
Answer» D. Process costing
454.

Under which method costs are collected & accumulated for each job: -

A. Job Costing
B. Contract Costing
C. Batch Costing
D. None of these
Answer» A. Job Costing
455.

The basis of collection of costs are:-

A. Materials
B. Wages
C. Overheads
D. All of these
Answer» D. All of these
456.

Which method is adopted to calculate the cost of each batch?

A. Contract Costing
B. Job Costing
C. Batch Costing
D. Job sheet
Answer» C. Batch Costing
457.

In what basis of work, the contractor is made payment?

A. Certified Work
B. Uncertified Work
C. National Profit
D. None of these
Answer» A. Certified Work
458.

Ascertainment of cost of the product at each process is called: -

A. Job Costing
B. Contract Costing
C. Process Costing
D. Batch Costing
Answer» C. Process Costing
459.

A contract account is a _______ account in nature.

A. Real a/c
B. Personal a/c
C. Nominal a/c
D. All of these
Answer» C. Nominal a/c
460.

Identify the types of specific order costing.

A. Job Costing
B. Batch Costing
C. Both (a) & (b)
D. Process Costing
Answer» C. Both (a) & (b)
461.

Which of the following is known as Terminal Costing?

A. Job Costing
B. Batch Costing
C. Process Costing
D. Contract Costing
Answer» D. Contract Costing
462.

The costing method which can be used in industry where the product pass through different processes is known as______.

A. job costing
B. operating costing
C. batch costing
D. process costing
Answer» D. process costing
463.

Process Account is _____.

A. Nominal A/c
B. Real A/c
C. Personal A/c
D. either Nominal or Real A/c
Answer» A. Nominal A/c
464.

Profit to be transferred to P& L A/c , if the contract is complete to the extent of only 20% is _____.

A. nil
B. 20%
C. 25%
D. 75%
Answer» A. nil
465.

If the actual loss is more than the estimated normal loss, then it is

A. abnormal loss
B. normal loss
C. seasonal loss
D. abnormal gain
Answer» A. abnormal loss
466.

The sum of value of work certified and uncertified appearing in the Contract Account is called

A. Work in Progress
B. Work in Process
C. Work completed
D. Work done
Answer» A. Work in Progress
467.

Contract costing is specialized system of job costing applies to _____ contracts.

A. Short-term
B. Medium-term
C. Long-term
D. Continuous process
Answer» C. Long-term
468.

Each job has a ______ prepare for it that bears the job number and which is used to collect all cost data relating to job.

A. Job time sheet
B. Job Cost Card
C. Job ticket
D. Job Account
Answer» B. Job Cost Card
469.

The first step in a job order cost procedure is

A. Receiving of order
B. Estimation of the price of the job
C. Production order
D. Receiving an enquiry
Answer» D. Receiving an enquiry
470.

Job Costing is suitable for

A. Ship-builders
B. Furniture makers
C. Printing presses
D. All of the above
Answer» D. All of the above
471.

Batch costing is a form of specific order/job costing where the cost per unit is ascertained by _________ the total cost of a batch by the number of items produced in that batch.

A. dividing
B. multiplying
C. subtracting
D. adding
Answer» D. adding
472.

The determination of EBQ is influenced by the following factors:

A. Rate of consumption
B. Manufacturing cost
C. Storage cost
D. All of the above
Answer» D. All of the above
473.

Work which has been done but not certified is called

A. Work uncertified
B. Work certified
C. Extra work
D. None of the above
Answer» A. Work uncertified
474.

The sum of value of work certified and uncertified appearing in the contract account is called

A. Work in process
B. Work completed
C. Work in progress
D. None of the above
Answer» A. Work in process
475.

Loss which unavoidable on account of inherent nature of production processes is

A. Abnormal loss
B. Normal loss
C. Process loss
D. None of the above
Answer» B. Normal loss
476.

In process costing when the actual loss is less than the normal loss then it is

A. Abnormal gain
B. Abnormal loss
C. Process gain
D. None of the above
Answer» A. Abnormal gain
477.

What we prepare for each job that bears the job number and which is used to collect all cost data relating to job is:

A. Job time sheet
B. Job cost card
C. Job ticket
D. Job account
Answer» B. Job cost card
478.

An automobile service unit uses:

A. Batch costing
B. Contract costing
C. Job
D. Specific order
Answer» B. Contract costing
479.

Where the work is undertaken to customer’s special requirements and each order is of comparatively short duration, then it is called:

A. Job costing
B. Batch costing
C. Operation costing
D. Output costing
Answer» A. Job costing
480.

Printing industry uses:

A. Job costing
B. Batch costing
C. Operation costing
D. Output costing
Answer» B. Batch costing
481.

Batch costing is a form of:

A. Process costing
B. Continuous process costing
C. Specific order costing
D. Operation costing
Answer» C. Specific order costing
482.

Batch costing is applied in:

A. Pharmaceutical industries
B. Computer industries
C. Toy making
D. All of the above
Answer» D. All of the above
483.

Batch costing is used for which type of product?

A. Heterogeneous product
B. By-product
C. Homogeneous product
D. All of the above
Answer» C. Homogeneous product
484.

Contract costing is a specialized system of Job costing applies to:

A. Short term contracts
B. Medium term contracts
C. Long term contracts
D. Continuous process
Answer» C. Long term contracts

Done Studing? Take A Test.

Great job completing your study session! Now it's time to put your knowledge to the test. Challenge yourself, see how much you've learned, and identify areas for improvement. Don’t worry, this is all part of the journey to mastery. Ready for the next step? Take a quiz to solidify what you've just studied.