84
78.5k

500+ Railway Engineering Solved MCQs

These multiple-choice questions (MCQs) are designed to enhance your knowledge and understanding in the following areas: Civil Engineering .

351.

A good ballast, when laid on formation, should have sufficient voids.

A. Yes
B. No
Answer» A. Yes
352.

Generally, the rail section is designed by assuming that it can bear a load equal to

A. 100 times
B. 350 times
C. 460 times
D. 560 times
Answer» D. 560 times
353.

The standard size of wooden sleepers on broad gauge railway track is

A. 1.52 m x 15 cm x 10 cm
B. 1.83 m x 20 cm x 11 cm
C. 2.74 m x 25 cm x 13 cm
D. any one of these
Answer» C. 2.74 m x 25 cm x 13 cm
354.

A track is laid over

A. sleepers
B. formation
C. rails
D. ballast
Answer» B. formation
355.

The number of dog spikes normally used per rail seat on curved track is

A. one on either side
B. one inside and two outside
C. one outside and two inside
D. two on either side
Answer» B. one inside and two outside
356.

The rail chairs are generally made of

A. cast iron
B. low carbon steel
C. high carbon steel
D. stainless steel
Answer» A. cast iron
357.

The switch angle is the angle subtended between the gauge faces of the

A. tongue rail and check rail
B. stock rail and check rail
C. stock rail and tongue rail
D. none of these
Answer» A. tongue rail and check rail
358.

The level of both the rails on straight lengths should be different.

A. True
B. False
Answer» B. False
359.

The minimum value of flangeway clearance is

A. 60 mm
B. 80 mm
C. 100 mm
D. 120 mm
Answer» A. 60 mm
360.

Anchors are also known as anti - creepers.

A. Correct
B. Incorrect
Answer» A. Correct
361.

Rail chairs are used to fix

A. flat footed rails
B. bull headed rails
C. double headed rails
D. none of these
Answer» C. double headed rails
362.

Charles Vignole invented

A. double headed
B. bull headed
C. flat footed
Answer» C. flat footed
363.

The main purpose of using bering plates is to

A. distribute the pressure over wider area
B. eliminate the adzingt of wooden sleepers
C. prevent the widening of gauge of curves
D. all of these
Answer» D. all of these
364.

The speed of a locomotive, in India, on metre gauge is restricted up to

A. 60 km/h
B. 80 km/h
C. 100 km/h
D. 120 km/h
Answer» B. 80 km/h
365.

The ballast material generally used on Indian railways consist of

A. broken stone
B. gravel
C. moorum
D. all of these
Answer» D. all of these
366.

The chief function of sleepers is to

A. support the rails
B. keep the two rails at correct gauge
C. distribute the load coming on rails to the ballast
D. all of the above
Answer» D. all of the above
367.

A three-throw requires

A. two sets of switches and two crossings
B. three sets of switches and two crossings
C. two sets of switches and three crossings
D. three sets of switches and three crossings
Answer» C. two sets of switches and three crossings
368.

On Indian railways, the number of fish bolts used to connect one pair of fish plates to the rails are

A. two
B. four
C. six
D. eight
Answer» B. four
369.

Which of the following statement is wrong?

A. The pot sleepers can be used if degree of the curve is more than 4?
B. Track circuiting is not possible in R.C.C. sleepers.
C. The effective bearing area of all types of sleepers is not the same.
D. all of the above
Answer» D. all of the above
370.

If ? is the switch angle and R is the radius of the turn out, the length of tongue rail will be

A. R tan ?
B. R tan ? / 2
C. R cot ?
D. R cot ? / 2
Answer» B. R tan ? / 2
371.

For new embankments in black cotton soil, the material used as blanket is

A. sand
B. moorum
C. coal ash
D. broken stone
Answer» B. moorum
372.

In India, the ruling gradient provided in plains for one locomotive train, is

A. 1 in 150 to 1 in 200
B. 1 in 200 to 1 in 250
C. 1 in 250 to 1 in 300
D. 1 in 300 to 1 in 350
Answer» A. 1 in 150 to 1 in 200
373.

The holding power of screw spikes is less than dog spikes.

A. Yes
B. No
Answer» B. No
374.

When one track is superimposed on the other track, it is known as

A. ladder track
B. double slip track
C. Gaunlet track
D. none of these
Answer» C. Gaunlet track
375.

The flow of rail metal due to abnormally heavy loads is called

A. hogging
B. buckling
C. wear of rails
D. creeping
Answer» C. wear of rails
376.

Which of the following statement is correct?

A. Bull headed rails keep better alignment than flat footed rails due to chairs.
B. Flat footed rails are cheaper than bull headed rails.
C. Flat footed rails are stronger in every direction than the bull headed rails for the same cross-sectional area.
D. all of the above
Answer» D. all of the above
377.

The width of platform, under no circumstances, should be less than

A. 2 m
B. 4 m
C. 6 m
D. 8 m
Answer» B. 4 m
378.

A cross-over requires

A. two sets of switches and two crossings
B. two sets of switches and four crossings
C. four sets of switches and four crossings
D. none of these
Answer» A. two sets of switches and two crossings
379.

The bearing plates are used to fix

A. flat footed
B. bull headed
C. double headed
Answer» A. flat footed
380.

Minimum packing space provided between two sleepers is

A. 250 to 300 mm
B. 300 to 350 mm
C. 350 mm to 400 mm
D. 400 to 450 mm
Answer» B. 300 to 350 mm
381.

Under the sleepers,

A. boxing
B. packing
Answer» B. packing
382.

The minimum depth of ballast for broad gauge tracks on Indian railways is

A. 200 mm
B. 250 mm
C. 300 mm
D. 350 mm
Answer» B. 250 mm
383.

The distance between the running edge of the stock and switch rails at the switch heel, is called

A. heel clearance
B. heel divergence
C. heel spacing
D. either (a) or (b)
Answer» D. either (a) or (b)
384.

In India, the sleeper density provided is

A. 18 sleepers per rail length
B. 25 sleepers per rail length
C. 28 sleepers per rail length
D. 40 sleepers per rail length
Answer» A. 18 sleepers per rail length
385.

For broad gauge main lines with maximum traffic loads, the rail section provided should have

A. 29.77 to 37.25 kg/m
B. 44.7 to 56.8 kg/m
C. 49.8 to 52.3 kg/m
D. 49.8 to 56.8 kg/m
Answer» B. 44.7 to 56.8 kg/m
386.

Which of the following statement is correct?

A. The ruling gradient is maximum gradient to which the track may be laid
B. In order to avoid the resistance after a certain limit, gradients on curves are reduced
C. Grade compensation is denoted by percentage per degree of curve.
D. all of the above
Answer» D. all of the above
387.

The wooden sleepers are the ideal sleepers

A. Yes
B. No
Answer» A. Yes
388.

The standard width of ballast for broad gauge track on Indian railways, is

A. 2.3 m
B. 2.9 m
C. 3.35 m
D. 5.53 m
Answer» C. 3.35 m
389.

According to Indian Railways Board, the minimum distance between the centre to centre of two tracks for broad gauge is

A. 4.725 m
B. 6.1 m
C. 7.49 m
D. 10.82 m
Answer» A. 4.725 m
390.

The composite sleeper index determines the

A. suitability of the wooden sleepers
B. number of sleepers per rail length
C. permissible stresses in the steel sleepers
D. all of these
Answer» A. suitability of the wooden sleepers
391.

Between two rails, a gap of

A. 1.5 mm to 3 mm
B. 3 mm to 6 mm
C. 6 mm to 9 mm
D. 9 mm to 12 mm
Answer» A. 1.5 mm to 3 mm
392.

The rail section is divided on the basis of

A. type of rails
B. spacing of sleepers
C. gauge of the track
D. speed of trains
Answer» C. gauge of the track
393.

The distance between the adjacent faces of the stock rail and the check rail, is called

A. heel divergence
B. heel clearance
C. flangeway clearance
D. throw of switch
Answer» C. flangeway clearance
394.

The number of sleepers used per rail length on the track is known as

A. sleeper strength
B. sleeper density
C. sleeper ratio
D. all of these
Answer» B. sleeper density
395.

The standard size of wooden sleepers on metre gauge railway track is

A. 1.52 m x 15 cm x 10 cm
B. 1.83 m x 20 cm x 11 cm
C. 2.74 m x 25 cm x 13 cm
D. any one of these
Answer» B. 1.83 m x 20 cm x 11 cm
396.

For station yards, Indian railways have recommended a gradient of

A. 1 in 100
B. 1 in 200 to 1 in 250
C. 1 in 500
D. 1 in 1000
Answer» D. 1 in 1000
397.

The longitudinal movement of the rails in a track is technically known as

A. buckling
B. hogging
C. creeping
D. none of these
Answer» C. creeping
398.

The heel divergence is always

A. equal to
B. less than
C. greater than
Answer» C. greater than
399.

The bull headed rails are provided on points and crossings.

A. Yes
B. No
Answer» A. Yes
400.

Which of the following statement is wrong?

A. The length of gap at crossing between two noses of a diamond crossing increases as the crossing angle decreases.
B. The sand hump is a device to check the movement of a vehicle.
C. The next signal after outer signal towards station is a routing signal.
D. A stop signal placed at the end of a platform is called a starter signal.
Answer» C. The next signal after outer signal towards station is a routing signal.

Done Studing? Take A Test.

Great job completing your study session! Now it's time to put your knowledge to the test. Challenge yourself, see how much you've learned, and identify areas for improvement. Don’t worry, this is all part of the journey to mastery. Ready for the next step? Take a quiz to solidify what you've just studied.