Slack time refers to
Q.
Slack time refers to
A.
An activity
B.
An event
C.
Both event and activity
D.
None of the above
Answer» B. An event
694
0
Do you find this helpful?
6
View all MCQs in
Construction Management
Discussion
No comments yet
Login to comment
Related MCQs
If TL is the latest allowable event occurrence time, total activity slack(s), is equal to
Optimistic time, most likely time and pessimistic times for the activities of a network in the given figure are written above their arrows. If the contractual obligation time for the project is 75, the latest occurrence time for the event 2, is
If a is the optimistic time, b is the pessimistic time and m is most likely time of an activity, the expected time of the activity, is
For a given activity, the optimistic time, pessimistic time and the most probable estimates are 5, 17 and 8 days respectively, The expected time is
If the scheduled completion time of a project is more than the earliest expected time for completion of the project, then the probability of completion of the project within the scheduled completion time will be
The time with which direct cost does not reduce with the increase in time is known as
The time by which activity completion time can be delayed without affecting the start of succeeding activities, is known as
Assertion (A): Activity 57 is critical. Reason (R): Earliest finish time and latest finish time for events 57 are same Select the correct answer.
If the expected time for completion of a project is 10 days with a standard deviation of 2 days, the expected time of completion of the project with 99.9% probability is
The three time estimates for the activities of the network shown in the given figure are shown above their arrows. The earliest expected time for the event 4, is