320+ Project Management Solved MCQs

201.

Costs that are not directly related to the products or services of the project, but are indirectly related to performing the project.

A. Intangible Costs
B. Sunk Cost
C. Tangible Costs
D. Indirect Costs
Answer» D. Indirect Costs
202.

Relationship based on unrelated level of activity and past data of cost is measured with help of

A. cost estimation
B. price estimation
C. unit estimation
D. production estimation
Answer» A. cost estimation
203.

In estimation of cost functions, variations in a single activity level represents the

A. related total costs
B. related fixed cost
C. related variable cost
D. related per unit cost
Answer» A. related total costs
204.

The latest finish time for an activity:

A. Equals the min. of LFT − t for all immediate successors
B. Equals the max. of LFT − t for all immediate predecessors.
C. Equals the max. of EST + t for all immediate predecessors.
D. Equals the min. of EST + t for all immediate successors.
Answer» A. Equals the min. of LFT − t for all immediate successors
205.

Which of the following statements is true?

A. PERT is considered as a deterministic approach and CPM is a probabilistic techniques.
B. PERT is considered as a probabilistic techniques and CPM is considered as a deterministic approach.
C. PERT and CPM are both probabilistic techniques.
D. PERT and CPM are both considered as deterministic approachs.
Answer» B. PERT is considered as a probabilistic techniques and CPM is considered as a deterministic approach.
206.

In corporate costs, cost incurred to finance construction of new equipment are classified as

A. treasury costs
B. discretionary costs
C. human resource management costs
D. corporate administration costs
Answer» A. treasury costs
207.

An uncertain event or condition that, if it occurs, has a positive or negative effect on a project objectives is termed.

A. Random Chance
B. Disaster
C. Risk
D. Hazard
Answer» C. Risk
208.

The cost impact of a risk event occurring as a project proceeds through its life cycle tends to

A. Slowly rise
B. Slowly drop
C. Drop sharply and then level out
D. Rise sharply and then level out
Answer» A. Slowly rise
209.

Evaluation process of proposed projects or groups of projects is known as:

A. Project Analysis
B. Project Compilation
C. Project selection
D. Project Documentation
Answer» C. Project selection
210.

Nature of interrelationships between components in a system defines the

A. Function of system
B. Structure of system
C. Environment of system
D. Platform of system
Answer» B. Structure of system
211.

Listing goals of each existing and proposed project is first step in

A. Data Collection
B. Establishment of Project council
C. Prioritizing the projects
D. Identification of project categories
Answer» D. Identification of project categories
212.

For any project word objective is held to be synonymous with

A. Fact
B. Option
C. Opinion
D. Assumption
Answer» A. Fact
213.

Which of these is not one of the constraints of a project?

A. Scope
B. Resources
C. Team
D. Budget
Answer» C. Team
214.

Which of the following is not correct about initial phase of a project?

A. The cost associated at the beginning of the project is highest.
B. Stakeholders have maximum influence during this phase
C. The highest uncertainty is at this stage of the project.
D. All the above statements are correct.
Answer» A. The cost associated at the beginning of the project is highest.
215.

Which is the first stage in the project management model?

A. Understanding the project environment
B. Project definition
C. Project control
D. Project planning
Answer» A. Understanding the project environment
216.

A clear hierarchy of objectives in the project definition would NOT normally contain:

A. The purpose
B. An End result
C. Success criteria
D. Control mechanisms
Answer» D. Control mechanisms
217.

Which of the following is a factor that influences project selection?

A. Perceived and real needs
B. List of potential and ongoing projects
C. Current organizational environment
D. All of the above
Answer» D. All of the above
218.

The primary deliverable from the project identification and selection phase is a:

A. schedule of specific IS development projects.
B. Statement of Work.
C. mission statement.
D. design strategy.
Answer» A. schedule of specific IS development projects.
219.

When classifying and ranking projects, which of the following refers to the amount and type of resources the project requires and their availability?

A. Value chain availability
B. Business placement
C. Resource availability
D. Potential benefits
Answer» C. Resource availability
220.

When classifying and ranking projects, which of the following refers to the extent to which the project is viewed as helping the organization achieve its strategic objectives and longterm goals?

A. Resource availability
B. Business placement
C. Strategic alignment
D. Potential benefits
Answer» C. Strategic alignment
221.

During feasibility analysis it is necessary to examine several alternative solutions because
(i) a comparison of alternatives will lead to a cost-effective solution
(ii) a pre-conceived single solution may turn out to be unimplementable
(iii) it is always good to examine alternatives
(iv) management normally looks at alternatives

A. i and iii
B. i and iv
C. i and ii
D. ii and iv
Answer» C. i and ii
222.

Goals are identified by

A. discussion with all concerned
B. pinpointing unsatisfactory performance
C. finding poor management
D. examining a variety of documents
Answer» B. pinpointing unsatisfactory performance
223.

By technical feasibility of a solution we mean that

A. technology is available to implement it
B. persons are available to implement it
C. persons have technical ability to implement it
D. funds are available to implement it
Answer» A. technology is available to implement it
224.

By operational feasibility we mean

A. the system can be operated nicely
B. the system is unusable by operators
C. the system can be adapted by an organization without major disruptions
D. the system can be implemented
Answer» C. the system can be adapted by an organization without major disruptions
225.

By economic feasibility of a system we mean that

A. it is economical to operate
B. it is expensive to operate
C. it will be cost-effective if implemented
D. finances are available to implement the system and it will be cost – effective
Answer» D. finances are available to implement the system and it will be cost – effective
226.

The following are the most important points of a detailed system proposal
(i) who will supply and install the required equipment
(ii) cost-benefit analysis
(iii) comparison of alternative solutions
(iv) implementation plan

A. i, ii and iii
B. i, iii and iv
C. ii, iii and iv
D. ii and iii
Answer» C. ii, iii and iv
227.

At the end of the feasibility study the systems analyst

A. meets the users for a discussion
B. gives a summary feasibility report to the management
C. gives a systems proposal to management
D. tells the top management if the system is not feasible
Answer» B. gives a summary feasibility report to the management
228.

The process of determining whether an entrepreneur's idea is a viable foundation for creating a successful business is known as a:

A. feasibility analysis
B. business plan
C. strategic analysis
D. industry analysis
Answer» A. feasibility analysis
229.

A cost-benefit analysis is performed to assess

A. economic feasibility
B. operational feasibility
C. technical feasibility
D. all of the above
Answer» A. economic feasibility
230.

The primary objective of cost-benefit analysis is

A. to find out direct and indirect cost of developing the information system
B. to determine the tangible benefits of the information system
C. to determine if it is economically worthwhile to invest in developing the information system
D. to determine the intangible benefits of the information system
Answer» C. to determine if it is economically worthwhile to invest in developing the information system
231.

The following assumptions are made in case of break even analysis, except

A. All fixed costs are fixed
B. All variable costs are fixed
C. The prices of input factors are constant
D. Volume of production and volumes of sales are equal
Answer» B. All variable costs are fixed
232.

At breakeven point there is

A. Profit
B. Loss
C. No profit or loss
D. None of these
Answer» C. No profit or loss
233.

Which of the following should be taken into account when planning a project?

A. Social environment
B. Political environment
C. Operational environment
D. All of the above
Answer» D. All of the above
234.

Improvement efforts are determined by:

A. Criticality of problems
B. Current performance
C. Priorities for future output
D. All of the above
Answer» D. All of the above
235.

Performance measurement is:

A. The determination of improvement efforts.
B. The process of quantifying action.
C. The improvement of operations.
D. The planning and control of operations.
Answer» B. The process of quantifying action.
236.

Performance relating to the five operations’ objectives can be plotted on which type of diagram?

A. Quality
B. Outcome
C. Polar
D. Satisfaction
Answer» C. Polar
237.

Which kind of standards are those that are set arbitrarily to reflect some level of performance that is regarded as appropriate or reasonable?

A. Competitor performance standards
B. Target performance standards
C. Historical standards
D. Absolute performance standards
Answer» B. Target performance standards
238.

For a police department, using competitor performance standards, a competitor might be:

A. A fire service
B. A foreign police authority
C. A similar police department
D. All of the above
Answer» D. All of the above
239.

What approach is used to compare organisation operations with those of other companies?

A. SWOT analysis
B. PERT analysis
C. Benchmarking
D. Competitor performance assessment
Answer» C. Benchmarking
240.

The origins of benchmarking as it is used today go back to which company?

A. Microsoft
B. Toyota
C. Xerox
D. McDonald’s
Answer» C. Xerox
241.

A comparison between operations or parts of operations that are within the same total organisation is called:

A. Internal benchmarking
B. Competitive benchmarking
C. Non-competitive benchmarking
D. External benchmarking
Answer» A. Internal benchmarking
242.

Benchmarking against external organisations that do not compete directly in the same markets is called:

A. Non-competitive benchmarking
B. Collaborative benchmarking
C. Practice benchmarking
D. Non-assault benchmarking
Answer» A. Non-competitive benchmarking
243.

Which of the following is regarded as a fundamental flaw in the whole concept of benchmarking?

A. It limits improvements to currently accepted methods of operating.
B. It does not involve learning.
C. It limits critical thinking.
D. It is not a continuous process.
Answer» A. It limits improvements to currently accepted methods of operating.
244.

What matrix positions each factor according to its performance and its importance?

A. Competitive forces matrix
B. Performance importance matrix
C. Importance performance matrix
D. Customer assessment matrix
Answer» C. Importance performance matrix
245.

What do the letter ‘D’ and ‘I’ stand for in Deming’s cycle of improvement?

A. Design and improve
B. Develop and implement
C. Design and implement
D. Define and improve
Answer» D. Define and improve
246.

Ishikawa Diagrams are another name for what technique of improvement?

A. Cause-effect diagrams
B. Input-output analysis
C. Process maps
D. Scatter diagrams
Answer» A. Cause-effect diagrams
247.

The principles of the business process re-engineering (BPR) approach do NOT include:

A. Checking that all internal customers act as their own suppliers to identify problems.
B. Scrapping any process line over two years old and starting again from scratch.
C. Striving for improvements in performance by radical rethinking and redesigning the process.
D. Rethinking business processes cross-functionally to organise work around natural information flows.
Answer» B. Scrapping any process line over two years old and starting again from scratch.
248.

Qualifying competitive factors are those which:

A. Directly win business for the operation.
B. Need to be better than a good industry standard.
C. Are relatively unimportant compared with the others.
D. May not win extra business if the operation improves its performance but can certainly lose business if performance falls below a particular point.
Answer» D. May not win extra business if the operation improves its performance but can certainly lose business if performance falls below a particular point.
249.

Which of the following is not a tool and technique used in the process of Plan Risk Responses

A. Contingent Response Strategies
B. Expert Judgment
C. Risk and Impact Matrix
D. Strategies for positive risks or opportunities
Answer» C. Risk and Impact Matrix
250.

During which stage of Risk planning are modeling techniques used to determine overall effects of risks on project objectives for high probability, high impact risks?

A. Identify Risks
B. Plan Risk responses
C. Perform Qualitative risk analysis
D. Perform Quantitative risk analysis
Answer» D. Perform Quantitative risk analysis
251.

Supplier risk is highest with ___________.

A. Cost plus incentives fee.
B. Cost sharing.
C. Firm fixed price contract.
D. Fixed price plus incentives.
Answer» C. Firm fixed price contract.
252.

You have just completed Qualitative Risk Analysis of the project. What should you be doing next?

A. Plan Risk Management
B. Perform Quantitative Risk Analysis
C. Plan Risk Responses
D. Control Risks
Answer» B. Perform Quantitative Risk Analysis
253.

Risk Management Plan may include

A. Budgeting, Timing, Thresholds, Methodology
B. Risks, Triggers, Inputs to other processes
C. Avoided, Transferred, Mitigated and Accepted Risks
D. Risk Response Audits, Earned Value Analysis, Technical Performance Measurement
Answer» A. Budgeting, Timing, Thresholds, Methodology
254.

Reserve analysis is NOT a Tool/Technique in which of the following processes?

A. Cost Estimation
B. Activity Duration estimation
C. Cost Budgeting
D. Activity Resource Estimation
Answer» D. Activity Resource Estimation
255.

Which of the following is not a tool or technique used during the Risk Quantification Process?

A. Risk Categorization
B. Contingency planning
C. Probability and Impact Matrix
D. Risk Data Quality Assessment
Answer» B. Contingency planning
256.

Risk management is responsibility of the

A. Customer
B. Investor
C. Developer
D. Project team
Answer» D. Project team
257.

What is associated with product risk?

A. Control of test item
B. Negative consequences
C. non-availability of test environment
D. Test object
Answer» D. Test object
258.

A ____________ is a temporary endeavor undertaken to create a unique product service or result.

A. Assignment
B. Product
C. Research
D. Project
Answer» D. Project
259.

Assembling project team and assigning their responsibilities are done during which phase of a project management?

A. Initiation
B. Planning
C. Execution
D. Closure
Answer» A. Initiation
260.

The basic nature of a project is a/an _____ one.

A. permanent
B. temporary
C. (A) or (B)
D. Both (A) and (B)
Answer» B. temporary
261.

The structure of a project will vary depending on the _________to provide.

A. benefits it is intended
B. Structure
C. Schedule
D. Assignment
Answer» A. benefits it is intended
262.

A process that involves continuously improving and detailing a plan as more detail become available is termed as

A. project analysis
B. project enhancing
C. progressive deliberation
D. progressive elaboration
Answer» D. progressive elaboration
263.

A program is usually a group of

A. plans
B. people and work
C. related projects
D. unrelated projects
Answer» C. related projects
264.

Which from the following statement(s) is/are NOT true?
I. Projects have defined objectives
II. Programs have a larger scope than projects
III. The projects and programs in a portfolio must be directly related

A. I only
B. II only
C. III only
D. II and III only
Answer» C. III only
265.

Projects management is divided in _____ process groups.

A. 5
B. 7
C. 9
D. 11
Answer» A. 5
266.

____________are avoided by providing more tangible and objective results troughout the life cycle.

A. Adversarial stakeholder relationship
B. Documents
C. Preview
D. risk resolution
Answer» A. Adversarial stakeholder relationship
267.

.If any one factor of a project changes, _____ other factor(s) is/are likely to be affected.

A. all
B. one
C. at least one
D. at most one
Answer» C. at least one
268.

Business Value =

A. Tangible Elements
B. Intangible Elements
C. Tangible Elements – Intangible Elements
D. Tangible Elements + Intangible Elements
Answer» D. Tangible Elements + Intangible Elements
269.

Which from the following is NOT a tangible element?

A. Fixtures
B. Trademarks
C. Monetary assets
D. Stockholder equity
Answer» B. Trademarks
270.

A horizontal bar chart that shows project tasks against a calendar is called

A. milestone
B. goal
C. Gantt chart
D. PERT chart
Answer» C. Gantt chart
271.

Which from the following represents the correct project cycle?

A. Planning→Initiating→Executing→Closing
B. Planning→Executing→Initiating→Closing
C. Initiating→Planning→Executing→Closing
D. Initiating→Executing→Planning→Closing
Answer» C. Initiating→Planning→Executing→Closing
272.

The strategy used to correct resource over-allocations by balancing demand for resources and the available supply is known as

A. resource assignment
B. resource leveling
C. resource splitting
D. resource scheduling
Answer» B. resource leveling
273.

The statistical tool that depicts a project’s tasks and the relationships between those tasks is known as

A. milestone
B. goal
C. Gantt chart
D. PERT chart
Answer» D. PERT chart
274.

Which of the following is NOT a part of project management?

A. initiating
B. monitoring
C. closing
D. All above are parts
Answer» D. All above are parts
275.

The scope of the work is defined in which phase of the project management?

A. Initiating
B. Planning
C. Executing
D. Closing
Answer» A. Initiating
276.

How the project work will be carried out, monitored, and controlled? These questions are answered in which phase of the project management?

A. Initiating
B. Planning
C. Executing
D. Closing
Answer» B. Planning
277.

The review of the successes and the mistakes is normally held during _____ phase.

A. initiation
B. planning
C. execution
D. closure
Answer» D. closure
278.

The business case and the justification for the project is determined during the _____ phase.

A. initiation
B. planning
C. execution
D. closure
Answer» A. initiation
279.

According to Olivier Mesly, the 4 P’s critical for the success of a project are:

A. plan, processes, people, policy
B. plan, processes, people, power
C. plan, processes, potential, policy
D. plan, processes, potential, power
Answer» B. plan, processes, people, power
280.

Developing a technology is an example of

A. Process
B. Project
C. Scope
D. All of the above
Answer» B. Project
281.

The project life cycle consists of

A. Understanding the scope of the project
B. Objectives of the project
C. Formulation and planning various activities
D. All of the above
Answer» D. All of the above
282.

Following is(are) the responsibility(ies) of the project manager.

A. Budgeting and cost control
B. Allocating resources
C. Tracking project expenditure
D. All of the above
Answer» D. All of the above
283.

Following are the phases of Project Management Life Cycle. Arrange them in correct order Design, 2. Marketing, 3. Analysis and evaluation, 4. Inspection, testing and delivery

A. 3-2-1-4
B. 1-2-3-4
C. 2-3-1-4
D. 4-3-2-1
Answer» A. 3-2-1-4
284.

Design phase consist of

A. Input received
B. Output received
C. Both (A) and (B)
D. None of the above
Answer» C. Both (A) and (B)
285.

Project performance consists of

A. Time
B. Cost
C. Quality
D. All of the above
Answer» D. All of the above
286.

Five dimensions that must be managed on a project

A. Constraint, Quality, Cost, Schedule, Staff
B. Features, Quality, Cost, Schedule, Staff
C. Features, priority, Cost, Schedule, Staff
D. Features, Quality, Cost, Schedule, customer
Answer» B. Features, Quality, Cost, Schedule, Staff
287.

Resorce requirement in project becomes constant while the project is in its _____ progress stage.

A. 40 to 55%
B. 55 to 70%
C. 70 to 80%
D. 80 to 95%
Answer» D. 80 to 95%
288.

The probability of completing the project can be estimated based upon the ____ .

A. Uniform distribution curve
B. Normal distribution curve.
C. U-shaped distribution curve
D. None of the above
Answer» B. Normal distribution curve.
289.

In the initial stage of the project the probability of completing the project is ___ .

A. Zero
B. High
C. Low
D. Any of the above
Answer» C. Low
290.

Each component of the software product is separately estimated and the results aggregated to produce an estimate for the overall job.

A. Algorithmic model
B. Expert judgment
C. Bottom-up
D. Top down
Answer» C. Bottom-up
291.

Following is (are) the component(s) of risk management

A. Risk Assessment
B. Risk Control
C. Risk Ranking
D. All of the above
Answer» D. All of the above
292.

Following are the characteristics of Project Mindset.

A. Time, Responsiveness, Information sharing, Processes, structured planning
B. Time, Project management, Information sharing, Processes, structured planning
C. Time, Responsiveness, Information sharing, capability, structured planning
D. Time, Responsiveness, Information sharing, Processes, project planning
Answer» A. Time, Responsiveness, Information sharing, Processes, structured planning
293.

“Devising and maintaining a workable scheme to accomplish the business need” is

A. Initiating process
B. Planning process
C. Executing process
D. Controlling process
Answer» B. Planning process
294.

Which one of the following is not an attribute of a project?

A. Definite starting date
B. Has no definite end date
C. Creates a product, service, or result
D. Requires resources
Answer» B. Has no definite end date
295.

Which one of the following is not a characteristic of a Project?

A. Temporary nature
B. Familiarity
C. Risk
D. Uniqueness
Answer» B. Familiarity
296.

_________comprehensive and flexible system for achieving, sustaining and maximizing business success

A. Statistical Sampling
B. Six sigma 9s quality
C. Six Sigma
D. Risk
Answer» C. Six Sigma
297.

Which of the following is responsible for the quality of the project deliverables?

A. The project champion
B. The project team
C. Stakeholders
D. Customers
Answer» B. The project team
298.

Which of the following is an example of internal failure cost?

A. Rework
B. Quality audits
C. Random quality audits
D. Project team training
Answer» A. Rework
299.

QC is typically a(n) _______________ process.

A. Management
B. Project manager
C. Audit
D. Inspection
Answer» D. Inspection
300.

In quality management, which of the following is not an attribute of the cost of nonconformance?

A. Loss of customers
B. Downtime
C. Safety measures
D. Rework
Answer» C. Safety measures
Tags
Question and answers in Project Management, Project Management multiple choice questions and answers, Project Management Important MCQs, Solved MCQs for Project Management, Project Management MCQs with answers PDF download